# Deleting Counters and/or Changing Counter method 3\.0

## Overview

You are using, for example, Infeed - Reject and you want to change to, for example, Infeed - Outfeed.

Note :

1) stop all production runs for the equipment in question before changing the Counter
2) uncheck the Equipment in the Material Manager (deletes associated OEE Operation)

3) change the Counters (enable/disable/delete whichever works for you)

4) restart the Production Module from the Gateway

5) re-assign the Material(s) and make sure the correct Count Equipment are selected
![](/resources/Storage/knowledge-base/deleting-counters-and-or-changing-counter-method-3-0/image2022-12-28_14-23-13.png)

### Applies To and Version Info

3.0

## Details

Production Model Counter Tab

for Infeed - Reject

![](/resources/Storage/knowledge-base/deleting-counters-and-or-changing-counter-method-3-0/image2022-12-28_14-24-0.png)

for Infeed - Outfeed (note Reject will be calculated)

![](/resources/Storage/knowledge-base/deleting-counters-and-or-changing-counter-method-3-0/image2022-12-28_14-24-25.png)

## Explanation

Unfortunately, the Historical Analysis will not show a breakdown between the different runs. This is working as designed.

If the line has Reject Counters, use them (Infeed - Reject). Else calculate Reject (Infeed - Outfeed). 

We look for any Reject Counters on the line or any cells **at the time** the Analysis is run.

If **at the time** Analysis is run there are no Reject counts, we will calculate Reject based on Infeed - Outfeed.