Tracking Multiple Changeover Modes for a Single Production Run 3.0

You want to be be able to setup multiple different types of changeover modes that will occur in a work order

Step-by-step guide

The stock changeover functionality only supports one changeover type segment per production run. 

Each segment has it's own equipment mode that it writes for the relevant equipment, therefore one changeover per run.

But the model can also support more than two segments per operation, each with their own equipment mode value for the relevant equipment.  


Information

Here is how the operations segments could be configured to support this

Related articles

Alternatively, in the meantime, you can control the Equipment Mode directly via the Tag Collector Path, and therefore in that way drive the value however you like.